Juanita-Woodinville Wy. NE/NE 160th St. Pavement Overlay Project

This project will pave roads on:

  • Juanita-Woodinville Wy. NE between NE 145th St. and I-405
  • NE 160th St. between I-405 and 116th Ave. NE

Schedule

TimelineWhat's Happening

Spring/Summer 2020

City repaired and replaced existing storm drain facilities in the roadway to prepare for overlay work

March 5, 2021

City Council approved construction contract with Granite Construction

April 19, 2021

Construction started. Expect traffic delays through mid-June. Find alternative routes if possible.

Traffic Impacts

Please visit the Traffic Alerts page for traffic impacts related to this project.

Juanita Woodinville Overlay Vicinity Map

Funding

This project is funded in part by the Safe Streets & Sidewalks levy through the City's Pavement Preservation Program.