228th St SW/SE Pavement Preservation

This project will rehabilitate the pavement on multiple segments of 228th St SE/228th St SW and an adjacent section of 19th Ave SE. See the map below for project locations. The project consists of milling, spot repairs, pavement overlay and striping work for each impacted segment. 

Schedule

TimelineWhat's Happening

April 26, 2021

Construction started.

July 2021

Construction completed.


Traffic Impacts

Please visit the Traffic Alerts page for traffic impacts related to this project.

Map

228thPvmtPresVM


This project is funded in part by the Safe Streets & Sidewalks levy.